Avon Tyrrell Experiential Learning & Sports Centre
A transformative new facility for young people, combining experiential learning with state-of-the-art sports provision in the heart of the New Forest.
£4.5M
Total Project Cost (inc. VAT)
£2.67M
Fundraising (ex. mortgage)
£2.0M
Mortgage Facility
Apr 2029
Project Completion
Explore Dashboard
Executive Summary
Project status as at 24 August 2026. Fundraising: £854K secured & likely (net) + £486K weighted pipeline = £1.34M — worst-case gap £1.16M to the £2.5M target; best case ~£2.1M if everything in pipeline and public fundraising lands at 100%. FY26/27 actuals to 31 July (Xero): income £255K, expenditure £46K, surplus £209K. Project plan on track — 25% complete overall (Case for Support done; 99-yr lease workstream 36→63%). No Very High risks remain — A3 improved 16→12; A1 now classified High.
Overall Status AMBER
Schedule GREEN
Budget GREEN Finance: Under Review
Risk AMBER
Resources GREEN
Fundraising in-house — Joe Trueman appointed Capital Appeal Trust & Foundation Lead (internal); consultant contracts ended as planned, savings reflected in budget
£
£4.5M
Total Project Cost (inc. VAT)
Income £4.67M vs expenditure £4.47M · ~£200K contingency
📈
£854K
Secured & Likely (net)
34% of £2.5M fundraising target · net of event costs · incl. Bernard Sunley £100K
⚠
18
Active Risks
0 Very High • 3 High • 10 Medium • 5 Low (A3 ↓ 16→12 · no Very High)
Ask £250K · revised proposal by mid-Sep · decision Nov 2026
Jack Petchey Foundation
£80K
80% weighted
Ask £100K · submitted · awaiting decision
Grants in Development
£115K
weighted
Garfield Weston (on hold until 50% secured) · National Lottery · Postcode Innovation
2027 Events Pipeline
£91K
weighted
Supercar Driver Club track day · Zach's Garage · James Skziller
Youth Matters Fund — Prospect
£500K
potential · not in figures
SIB bidding to DCMS · eligibility known end 2026 · Jacob influencing
Scenarios: worst case £1.34M (secured + weighted) leaves a £1.16M gap · best case ~£2.1M if all pipeline (£1.17M ask) and public fundraising ideas (£105K) land at 100% — public fundraising needs additional resource in Sam's team / at AT · Youth Matters Fund could be a major further opportunity
RIBA Project Stage — click for timeline
Decisions Required — next FRACo 8 Sep 2026
T&F Actions Log — per May 2026 meeting · blue = complete · green = ongoing / on track · amber = at risk
ID
Action
Owner
Status
Notes
Team & Capacity — linked to risk A4 (Resourcing, High)
Capital Appeal Trust & Foundation Lead
Joe Trueman
Internal appointment — bids written in-house
Corporate Partnerships
Theo Fox (permanent)
AT & Outdoor Learning focus — site visited
Consultants
None
Contracts ended as planned — staffing savings reflected in budget
Staffing Budget
£21K across 3 years — in-house model (was £65K with consultants)
Supporting Team
Vicky · David · Caroline · Rosie — risk owners
Budget Overview
Three-year capital appeal financial plan 2026–2029
£4.67M
Total Income (3-Year)
£174K above target (incl. 25/26 income) · click for breakdown
£4.47M
Total Expenditure (3-Year)
~£200K surplus / contingency
£3.39M
Build Costs (FY27/28)
Click for breakdown
£2.0M
Mortgage Facility
Click for breakdown
FY 2026/27
FY 2027/28
FY 2028/29
3-Year Summary
FY 2026/27 Actuals vs Budget — per Xero, as at 31 July 2026
Income to Date
£255K
~15% of £1.75M FY26/27 income budget
Expenditure to Date
£46K
~12% of £375K FY26/27 expenditure budget
Surplus to Date
£209K
Income running ahead of expenditure phasing
Income — FY 2026/27
Source
Pre-Apr 2026
FY 26/27
Cumulative
Trusts & Foundations
—
£750,000
£750,000
Corporate Partnerships
—
£250,000
£250,000
Supercar Driver Events*
—
£135,000
£135,000
Zach's Garage Fundraiser
—
£100,000
£100,000
Nigel Mansell Income
£24,200
£410,000
£434,200
Income for Fundraising Costs
—
£100,000
£100,000
Restricted Fund Drawdown
£369,500
—
£369,500
Total Income
£393,700
£1,745,000
£2,138,700
*Supercar income still being finalised — 169 tickets sold; gross could reach ~£200K vs £135K net budgeted.
Expenditure — FY 2026/27
Category
Pre-Apr 2026
FY 26/27
Cumulative
Staff Travel
£130
£6,000
£6,130
Mobile Phone
—
£180
£180
Consultants
—
£15,000
£15,000
Capital Appeal Events
—
£16,000
£16,000
Event Catering
—
£10,000
£10,000
Supercar Driver Events
—
£45,000
£45,000
Zach's Garage Events
—
£40,000
£40,000
Design & Marketing
—
£9,000
£9,000
Finance Arrangement Fees (loan)
—
£45,000
£45,000
Legal & Professional (incl. £28K lease)
£1,800
£28,000
£29,800
Build De-Risk
£12,800
—
£12,800
Professional Fees (Design Team)
—
£151,830
£151,830
Salaries (in-house bid writing)
—
£9,000
£9,000
Total Expenditure
£14,730
£375,010
£389,740
Quarterly Cost Phasing — FY 2026/27
Income — FY 2027/28
Source
Brought Forward
FY 27/28
Cumulative
Trusts & Foundations
£750,000
£500,000
£1,250,000
Corporate Partnerships
£250,000
—
£250,000
Supercar Driver Events
£135,000
—
£135,000
Zach's Garage Fundraiser
£100,000
—
£100,000
Nigel Mansell Income
£434,200
—
£434,200
Income for Fundraising Costs
£100,000
—
£100,000
Restricted Fund Drawdown
£369,500
—
£369,500
Mortgage (£2M)
—
£2,000,000
£2,000,000
Total Income
£2,138,700
£2,500,000
£4,638,700
3-Year Total (incl. £35K event income adjustments)
+£200,611 · previous £215K shortfall closed via higher Trusts target and staffing savings
3-Year Income & Expenditure Summary
Cash Flow & Sensitivity
Monthly cash position, cost phasing, VAT exposure and what-if scenarios
£2.33M
Peak Cash Balance
Sep 2027 (post-mortgage drawdown)
Positive
Cash Position — All 36 Months
Lowest point ~£166K (Feb 2029). Budget no longer dips below zero.
£200K
Surplus / Contingency
Income £4.67M vs expenditure £4.47M. Previous £215K shortfall closed.
£678K
VAT Recovery Opportunity
Worst case still assumed in budget. Any recovery adds directly to contingency.
Monthly Cash Position — Apr 2026 to Mar 2029
Note: Following the July 2026 budget rework, the cash position now stays positive across all 36 months and closes with a ~£200K contingency. The improvement comes from a higher Trusts & Foundations target in FY27/28 (+£400K) and staffing savings (consultants ended, bids in-house). Irrecoverable VAT (£678K) is still assumed at worst case — any recovery adds directly to the contingency. Income timing and amounts will flex as the appeal progresses; income delivery remains the key risk (see A1).
Monthly Cost Phasing — Full 36-Month View
Irrecoverable VAT Exposure (Monthly)
FY 27/28: £610,477 (peak month Oct 27 £78K) · FY 28/29: £67,831 (3-month lag tail)
Restricted vs Unrestricted Income
Restricted: £369.5K (Nigel Mansell fund + other) is ring-fenced for capital. Remaining £3.9M must be raised or borrowed and is subject to fundraising / loan covenant risk.
Sensitivity Modelling — Adjust assumptions to see impact
0£0K£500K
0 mo0 months6 mo
0%0%+20%
Lowest Cash Point
(£215K)
Feb 2029
First Negative Month
Sep 2028
Final Cash Position
(£215K)
Reserves Required
£215K
Fundraising Pipeline
Named prospects, secured income and weighted pipeline — sourced from Vicky's pipeline update, August 2026. £854K secured & likely (net) · £486K weighted pipeline · worst-case gap £1.16M · best case ~£2.1M.
Secured & likely £854K (net) + weighted pipeline £486K = £1.34M, leaving a worst-case gap of £1.16M. Best case ~£2.1M if all pipeline (£1.17M ask) and public fundraising ideas (£105K) land at 100% — still short of the £2.5M target.
Status Summary — August 2026
Named Prospect Pipeline — grouped by status · per August 2026 pipeline · Bradbury & Jack Petchey now 80% weighted
Funder / Donor
Source
Ask (£)
Likelihood
Weighted (£)
Next Step
Income Secured & Likely — £854K net to date — net of event costs · incl. Bernard Sunley £100K committed
Event
Date
Projected Gross
Status / Notes
Public Fundraising Ideas 2027–28 — £105K projected net · not in pipeline figures
Activity
Projected Net
Buy a Brick @ £200 (6 sold at 11 Aug; target 125)
£25,000
Local beneficiary / challenge events
£25,000
Sponsored sleepout (corporate partners)
£25,000
Local pledge dinner (Lord & Lady Manners to host?)
£20,000
Donate option on AT booking form
£10,000
Open days · funders circle · regular giving · milestone campaigns
TBC
Total quantified
£105,000
Caveat: pursuing these ideas would need additional dedicated resource in Sam's team / at Avon Tyrrell.
Prospect — Youth Matters Fund — not included in pipeline figures
£500K
potential · weighted at 10% in prospects only
Social Investment Business (SIB) is currently bidding to DCMS for the Youth Matters Fund. If Avon Tyrrell is included within the fund's geographical scope, this could be a major opportunity for the appeal.
Eligibility will not be known until the end of this calendar year
Funding would not be distributed until the beginning of next financial year (FY27/28)
Jacob holds the SIB relationship and is prioritising influencing as the bid progresses
On Hold / Declined Funders — per August 2026 pipeline · transparency on what's been tried
Funder
Outcome
Reason
Risk Register
18 active risks across 5 strategic categories — click any risk for details. Trend column compares August 2026 residual score to the July 2026 position: → unchanged · ↑ score increased · ↓ score decreased. This month: A3 Economic Downturn improved 16→12 (Very High → High) — no Very High risks remain; A1 Funding Shortfall reclassified High (score unchanged at 12); A4 mitigation updated — fundraising responsibility spread across the Director of Fundraising's team.
0
Very High Risk
3
High Risk
10
Medium Risk
5
Low Risk
Risk Heat Map (Residual)
Likelihood
5
10
15
20
25
4
8
12
16
20
3
6
9
12
15
2
4
6
8
10
1
2
3
4
5
1
2
3
4
5
Impact →
Full Risk Register
ID
Category
Risk
Owner
Inherent
Residual
Severity
Trend
A1
Financial
Funding Shortfall
Vicky
16
12
High
→
A2
Financial
Over-reliance on Single Funding Source
Vicky
6
4
Medium
→
A3
Financial
Economic Downturn / Funding Climate Shift
Vicky
16
12
High
↓
A4
Financial
Resourcing & Capacity Constraints
Vicky
16
9
High
→
A5
Financial
Donor Withdrawal
Vicky
12
4
Medium
→
B1
Financial (Loan)
Failure to Secure £2M Bank Loan
Caroline
10
6
Medium
→
B2
Financial (Loan)
Failure to Secure 99-Year Lease
David
10
8
Medium
→
C1
Operational / Financial
Cost Inflation / Budget Overrun
David
12
4
Medium
→
C2
Operational
Planning Permission Issues
David
9
1
Low
→
C3
Operational
Contractor Failure / Supply Chain
David
9
2
Low
→
C4
Operational
Programme Delays
David
4
1
Low
→
C5
Operational
H&S Incident During Build
David
9
4
Medium
→
C6
Operational
Environmental / Sustainability Compliance
David
6
2
Low
→
C7
Operational
Extreme Weather Impact
David
12
6
Medium
→
D1
Finance
Cash Flow Pressure
Caroline
6
4
Medium
→
D2
Strategic
Governance / Decision-Making Delays
Rosie
4
1
Low
→
E1
Financial
Revenue Underperformance
David
12
6
Medium
→
E2
Financial
New Build Demand Risk
David
6
4
Medium
→
×
Project Milestones & Timeline
Key delivery dates for the Avon Tyrrell Capital Appeal
RIBA Project Stage — Current Position
Legend
Status (circle colour)
Complete
On track
At risk
Off track
Workstream (tag next to name)
GovernanceDesignLoanFundraisingBuildCloseout
Workstream Progress — % complete per MS Project, August 2026 · all workstreams on track · ~25% overall
Fundraising45%
Lease (99yr)63%
Loan (£2M)30%
RIBA Stage 460%
Build13%
Recently Completed — all 100% per MS Project
Governance
FRACo Sign Off
24 Feb 2026 ✓
Initial project authorisation
Build
De-Risk Report Submission
10 Mar 2026 ✓
£12,810 actual cost
Governance
Trustee Board Green Light
12 Mar 2026 ✓
Board approval to proceed
Design
FRACo RIBA Stage 3 & 4 Costs
19 May 2026 ✓
£152K Stage 4 expenditure approved
Project Timeline — % complete per MS Project
Sep 2026
LoanPay Solicitors 60% 18 Sep 2026 — £28K lease legal fees; lease drafting 70% complete, for September Board